Shell – Puget Sound Refinery FCCU Revamp and Tar – 2019

Location: Anacortes, WA

Matrix Service completed the 2019 FCCU revamp and turnaround for Shell at the Puget Sound Refinery. The project included over 168,000 manhours; peak manpower was 178.



Turnaround - Reactor:

  • Hydro-cut and remove RX OH line for re-use
  • Hydro-cut and remove old RX head, shell and dragon head
  • Install New RX head, shell and dragon head
  • Install RX OH line
  • Tie in RX and steam piping



Turnaround - Regenerator:

  • Hydro-cut and remove Regen OH line for re-use
  • Hydro-cut and remove old Regen head
  • Hydro-cut and remove spent cat inlet pipe and air grid
  • Install new air grid and spent cat inlet pipe
  • Install new Regen head and cyclones
  • Install Regen OH line
  • Tie in Regen and steam piping
168000
manhours
100%
commitment to safety
0
indecent safety culture

Scope of Work

  • Fabricate new Regen head and cyclones
  • Fabricate new RX head and cyclones with upper plenum attached
  • Fabricate new Regen air-grid
  • Fabricate & install 300’ of 600# steam piping
  • Fabricate & install 1,430’ of Regen & RX piping
  • Air grid removal & replacement
  • Refractory repair on shell
  • Complete refractory repair on 6 cyclones

Put Our Standard
To The Test.

Get in touch with Matrix for your next project.
return to top icontop